Home
Overall Introduction
Background
Project 0bjectives
Project Cost and Financing
Project Design
Project Description
Resettlement
Project Benefits
Risks
 
 
 
 
 
Your Position - - Xiaolangdi Multipurpose Dam Project
Overall Introduction
The Xiaolangdi Multipurpose Dam Project is the only control project that provides a large storage capacity below Sanmenxia on the mainstream of the Yellow River. While enabling adequate flood control, it retains sediment by making use of the sediment storage, enabling water/sediment regulation and mitigating sedimentation on the downstream riverbed.
With sophisticated technologies, high degree of difficulties in construction, complicated relations of management in the field, and challenges in resettlement, the Project is considered as one of the most challenging schemes in the history of hydraulic engineering in the world.
The milestones of construction include: start of preparatory works in September 1991, commencement of main works in September 1994, achievement of river closure in October 1997, power generation connected to provincial grid of the first unit in January 2000, and total completion of main works in late 2001, with a schedule of 11 years. The work quantities include: 94.78 million m3 earth/rock excavation and backfill, 3.48 million m3 concrete, 30,000 t metal works, and 200,000 resettlers. The Project, which is completed ahead of schedule with cost saving and excellent quality, is appraised by the World Bank as an example of cooperation with the advancing countries.

 
 
Information Center of Xiaolangdi Multipurpose Project Construction & Administration Bureau ,YRCC¡¡
E-mail£ºWebadmin@xiaolangdi.com.cn